Bug
-
Resolution: Cannot Reproduce
-
Low
-
None
-
9.4.14
-
9.04
-
1
-
Severity 2 - Major
-
Issue Summary
When displaying Roadmap issue events (Jira) in Team Calendars (Confluence), the "target start" and "target end" dates for calendar events are exactly one day off.
This is reproducible on Data Center: Yes
Steps to Reproduce
Tested with Confluence 7.19.18 and Jira 9.4.14.
- Requires an application link between Jira and Confluence.
- In JIRA, create some issues with Roadmaps (Portfolio) feature that have a "Target start" and "Target end"
- In Confluence inside a Team Calendar, add Jira Issue Dates to your team calendar from JIRA project
Expected Results
The issue dates from Jira project should accurately reflect the start and end dates in Team Calendars.
Actual Results
The issue date events are exactly one day off.
Workaround
Currently there is no known workaround for this behavior. A workaround will be added here when available.
- relates to
-
CONFSERVER-54975 JIRA Issues Macro displays dates in Portfolio's "Target start" and "Target end" one day off
-
- Closed
-
- mentioned in
-
Page Loading...