As a GH user, I would like to specify if I want the burndown chart in hours or in days

    • Icon: Suggestion Suggestion
    • Resolution: Answered
    • None
    • None
    • None
    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      On the chartboard the burndown chart could be displayed with the remaining hours.
      However, for some teams a chart with remaining days is more useful.

          Form Name

            [JSWSERVER-2581] As a GH user, I would like to specify if I want the burndown chart in hours or in days

            This issue will not be addressed as it is related to Classic boards, which are no longer being improved and will be removed in the future. We encourage you to migrate to the new Agile boards for all future work.

            Regards,
            GreenHopper Team

            Michael Tokar added a comment - This issue will not be addressed as it is related to Classic boards, which are no longer being improved and will be removed in the future. We encourage you to migrate to the new Agile boards for all future work. Regards, GreenHopper Team

            Voting for this. It's one of the big requests I've had whilst implementing our JIRA setup.

            Alex Taylor added a comment - Voting for this. It's one of the big requests I've had whilst implementing our JIRA setup.