Advanced Roadmaps capacity distribution should honour changes made to the capacity of a team for a particular iteration/sprint and distribute work accordingly.

    XMLWordPrintable

Details

    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

    Description

      Problem Definition

      Currently, Advanced Roadmaps capacity distribution does not take into consideration updates made to the capacity of a team for a particular iteration or sprint and distribute the work to the rest of sprints/iterations. Having this ability would help in better planning, consider a situation where an iteration's capacity needs to be adjusted, for example when a developer is on leave, capacity distribution should consider this change and distribute the work accordingly to the rest of the iterations.

      Below are the screenshots showing current behaviour.

      Image #1 Showing capacity distribution with each iteration having the same capacity

      Image #2 Showing capacity distribution with a capacity of one of the iteration set to zero, we can see that it still has 20h of work assigned to the iteration.

      Suggested Solution

      Advanced Roadmaps Capacity distribution should honor changes made to the capacity of individual iteration and dynamically distribute the work-based to rest of the iterations to help planning work in an agile environment.