Uploaded image for project: 'Jira Software Data Center'
  1. Jira Software Data Center
  2. JSWSERVER-25047

Portfolio date picker does not honour all date formats that can be set up in the JIRA application

    XMLWordPrintable

Details

    Description

      NOTE: This bug report is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding bug report.

      Certain date formats that are accepted in JIRA as Date/Month/Year format are not accepted by Portfolio's date picker. The problem here was that the year format was specified in upper-case Ys (e.g., dd.MM.YYYY) which is correctly interpreted in JIRA but causes the date picker in Portfolio not to open / accept manually input dates.

      Workaround:
      Change the upper-case Y to lower-case y

      Original bug report:

      As far as I know, this is already known bug, however, I wasn't able to find it. We are not able to choose date from date time picker in any section of JIRA Portfolio. Could you please update us on this bug, is this fixed in some version or we should still wait? Regards, Jelena

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              6ad813ea2a30 Jelena Radovanovic
              Votes:
              14 Vote for this issue
              Watchers:
              15 Start watching this issue

              Dates

                Created:
                Updated: