    Suggestion 
- 
    Resolution: Unresolved
- 
    None
- 
        1
- 
        2
- 
        
NOTE: This suggestion is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding suggestion.
I am constantly scratching my head trying to figure out why certain items are scheduled later than i think they should be. What logic is being applied? Why is something so late? Why can't i bring it forward?
I often manage to derive the reason, after hours of trial and error, then write down a note to myself 'ah, check the rank' or 'check the dependency', or 'Portfolio honours X before Y'. I would like a report that explains step by step why Initiative 7 is scheduled for April 17th, how did Portfolio arrive at that conclusion?
- is duplicated by
- 
                    JPOSERVER-1834 Wrong Sorting Tasks on timeline according priority - Closed
 
- is related to
- 
                    JSWSERVER-25305 JIRA Portfolio Helper - Closed
 
- relates to
- 
                    JRACLOUD-88869 Report on how scheduling logic was applied - Closed
 