Stories closed in current sprint should contribute to capacity

XMLWordPrintable

    • 0

      NOTE: This suggestion is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding suggestion.

      I'm not sure if this is expected behaviour or not, but it is causing some confusion for our users:

      If a story is closed in the current sprint, it no longer shows in the schedule, and is removed from the capacity calculations. It's still visible in the scope section. This is problematic for us, as it then appears that there is available capacity in the sprint, when that's not the case.

      To address this, issues that are resolved in a sprint should continue to be visible in the schedule and they should continue to count towards the capacity utilisation for the sprint.

        1. 2017-04-27_17-04-06.png
          177 kB
          Mat Pemble (Adm)
        2. 2017-04-27_17-04-06.png
          212 kB
          Mat Pemble (Adm)

            Assignee:
            Unassigned
            Reporter:
            Maree Milne
            Votes:
            8 Vote for this issue
            Watchers:
            7 Start watching this issue

              Created:
              Updated:
              Resolved: