Incorrect scheduling with auto schedule

XMLWordPrintable

      Issue Summary

      When issues are scheduled in Portfolio using "Auto schedule" by following steps below, Portfolio schedule issue with more estimates in single Sprint.

      Steps to Reproduce

      1. Create a new Portfolio plan and connect it to a new Project.
      2. Create 4 Epics in the plan.
      3. Set 30 Story points for first 2 Epics & 20 Story points for the last 2 Epic's.
      4. Create 2 teams in the Portfolio plan.
      5. For each team set the Sprint velocity to 20 & Sprint length to 1 week
      6. Click on "Auto-schedule".

      Expected Results

      Portfolio schedule the Epic's to 2 separate Sprints since each Sprint is configured for 20 story points only and the first 2 Epics has more than 20 story points.

      Actual Results

      Workaround

      None.