Bug
-
Resolution: Unresolved
-
Low
-
None
-
8.20.0
-
8.2
-
1
-
Severity 3 - Minor
-
0
-
Issue Summary
When issues are scheduled in Portfolio using "Auto schedule" by following steps below, Portfolio schedule issue with more estimates in single Sprint.
Steps to Reproduce
- Create a new Portfolio plan and connect it to a new Project.
- Create 4 Epics in the plan.
- Set 30 Story points for first 2 Epics & 20 Story points for the last 2 Epic's.
- Create 2 teams in the Portfolio plan.
- For each team set the Sprint velocity to 20 & Sprint length to 1 week
- Click on "Auto-schedule".
Expected Results
Portfolio schedule the Epic's to 2 separate Sprints since each Sprint is configured for 20 story points only and the first 2 Epics has more than 20 story points.
Actual Results
Workaround
None.