Clicking confirm in Board configuration in new Date picker will not add highlighted date to configuration

XMLWordPrintable

    • Type: Bug
    • Resolution: Fixed
    • Priority: Low
    • 9.11.1, 9.12.0
    • Affects Version/s: 9.5.0, 9.10.0, 9.10.1
    • Component/s: Board configuration
    • None
    • 9.05
    • Severity 3 - Minor

      Issue Summary

      This is reproducible on Data Center: yes

      The bug appears in the Kanban/Scrum board setup where adding non-working days in the "Working days" section doesn't consistently function as expected. The highlighted current date requires an extra click for addition, and a similar issue arises when transitioning to the next or previous month

      Steps to Reproduce

      1. Go to Kanban/Scrum board configuration (Board needs to exist beforehand)
      2. Go to the "Working days" section
      3. Click "Add Date" button for Non-working days section
      4. Choose date and click confirm
      5. Click "Add Date" button for Non-working days section
      6. Click prev/next month button (the date is still highlighted) / Leave the default highlighet date (current date)
      7. Click confirm 

      Expected Results

      After confirmation, the date should be added. Only after clicking highlighted date once again, the date is added.

      Actual Results

      Highlighted date is not added without a manual click.

      Workaround

      Manually click highlighted date before clicking confirm.

              Assignee:
              Vadym Ohyr
              Reporter:
              Maria Marzec
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

                Created:
                Updated:
                Resolved: