Issue Summary
This is reproducible on Data Center: yes
The bug appears in the Kanban/Scrum board setup where adding non-working days in the "Working days" section doesn't consistently function as expected. The highlighted current date requires an extra click for addition, and a similar issue arises when transitioning to the next or previous month
Steps to Reproduce
- Go to Kanban/Scrum board configuration (Board needs to exist beforehand)
- Go to the "Working days" section
- Click "Add Date" button for Non-working days section
- Choose date and click confirm
- Click "Add Date" button for Non-working days section
- Click prev/next month button (the date is still highlighted) / Leave the default highlighet date (current date)
- Click confirm
Expected Results
After confirmation, the date should be added. Only after clicking highlighted date once again, the date is added.
Actual Results
Highlighted date is not added without a manual click.
Workaround