Thanks Alex.
In the meantime I will definitely look up the carry on feature.
Also, I figured out what was causing this issue and was able to correct it, which is not the right way to do it but it seemed to be the only solution.
The tasks that had the remaining values in the excel export, even though in the sub task it was 0, were on those sub tasks that were completed in previous iterations but migrated to the current iteration.
When I originally back dated the worklog to the date it was closed in the prior iteration. The current iteration didn't seem to recognize this.
To fix this:
1) I reopened all the sub-tasks that had the issue where remaining time was showing up in the excel report.
2) I had to edit the last work log, change the date to today's date or another date in the current iteration and kept the remaining time to 0.
3) Closed the sub tasks.
Once this was completed, the chart board was properly reflecting that these issues were closed with no additional time remaining.
Even though this is a work around for it, it shouldn't be doing it this way. Even if the sub task was zero'd in the previous iteration, it should just re-adjust how many hours to calculate for the current iteration and still show a proper burn down.
Thanks Alex.
In the meantime I will definitely look up the carry on feature.
Also, I figured out what was causing this issue and was able to correct it, which is not the right way to do it but it seemed to be the only solution.
The tasks that had the remaining values in the excel export, even though in the sub task it was 0, were on those sub tasks that were completed in previous iterations but migrated to the current iteration.
When I originally back dated the worklog to the date it was closed in the prior iteration. The current iteration didn't seem to recognize this.
To fix this:
1) I reopened all the sub-tasks that had the issue where remaining time was showing up in the excel report.
2) I had to edit the last work log, change the date to today's date or another date in the current iteration and kept the remaining time to 0.
3) Closed the sub tasks.
Once this was completed, the chart board was properly reflecting that these issues were closed with no additional time remaining.
Even though this is a work around for it, it shouldn't be doing it this way. Even if the sub task was zero'd in the previous iteration, it should just re-adjust how many hours to calculate for the current iteration and still show a proper burn down.