Summary
When an issue is split, the remaining estimate of the issue is not adjusted to reflect the changes in the Original Estimate.
Steps to reproduce:
- Set a Scrum board to use Original Estimate with Remaining Estimate as Estimate option.
- Access the backlog and set an estimate of an issue to 2weeks (example). Both Original & Remaining Estimates will be 2w.
- Right-click on the issue and click Split.
- Set the name of the split issue and adjust the estimate of the issue (1w + 1w as an example).
- Click save and check issue detail view of both issues. The remaining estimate of the original issue will remain at 2w.
Environment
JIRA 7.5 and above.
Expected Results
The Remaining Estimate is updated to reflect the changes with the Original Estimate
Possible solutions:
- Automatically adjust the remaining estimate
- Let the user input the remaining estimate during the split action
Actual Results
The Remaining Estimate is not updated to reflect the changes with the Original Estimate
Workaround
Manually edit the Remaining Estimate
- is related to
-
JSWSERVER-21820 Splitting an Issue may break the Burnup Chart
- Gathering Impact
-
JSWSERVER-14719 Splitting an estimated issue destroys burndown and velocity
- Closed
- relates to
-
JRASERVER-14360 Split issue
- Closed