Sprint End date disregards date picker advanced setting when duration is not custom

      Summary

      Sprint End date disregards date picker advanced setting when duration is not custom

      Steps to reproduce the problem

      1. Configure advanced configuration datepicker as follow:
        • jira.date.time.picker.java.format : dd.MM.yyyy HH:mm
        • jira.date.time.picker.javascript.format : %d.%m.%y %I:%M
      2. Create a sprint > allocate issues
      3. Start sprint > choose duration of 1 week (any option other than custom)

      Expected Result

      Date picker will show the date following the advanced configuration

      Actual Result

      Date picker does not follow the date picker format

      This problem does not happen if user choose custom duration as default:

      If the user chooses non-custom duration initially, and then switch back to custom, the end date will still show the wrong format of the year.

       

      Workaround

      1. Select "Custom" duration.
      2. In some cases, user will have to remove the AM or PM in the Start/End date.

        1. custom.png
          142 kB
        2. image-2017-04-14-16-24-48-363.png
          44 kB
        3. image-2017-04-14-16-32-16-743.png
          50 kB
        4. notcustom.png
          140 kB

              Unassigned Unassigned
              azuhra Aqqiela
              Affected customers:
              9 This affects my team
              Watchers:
              9 Start watching this issue

                Created:
                Updated: