Start Sprint date picker calendar disregards date picker advanced setting

      Summary

      Start sprint date picker calendar disregards date picker advanced setting

      Steps to reproduce

      1. Go to advanced setting and configure the following:
        • jira.date.time.picker.java.format : dd/MMM/yy HH:mm
        • jira.date.time.picker.javascript.format : %e/%b/%y %H:%M
      2. Go to planned sprint in the board > click Start sprint
      3. Select Start Date to load the calendar

      Expected result

      The time should be shown in 24 hours format in the calendar

      Actual Result

      The time is still shown in am/pm format in the calendar

            [JSWSERVER-15344] Start Sprint date picker calendar disregards date picker advanced setting

            Re. Katarina, we still have the same in 8.20.6. English-only Jira, but ISO8601 active.

            Janne Korkkula added a comment - Re. Katarina, we still have the same in 8.20.6. English-only Jira, but ISO8601 active.

            Katarina Larsson added a comment - - edited

            The same problem with the setting Use ISO8601 standard in Date Picker.

            Even if the setting is set to yes is the Sunday still the first day in the week.

            This is for Jira version 7.12.3 

            Katarina Larsson added a comment - - edited The same problem with the setting  Use ISO8601 standard in Date Picker. Even if the setting is set to yes is the Sunday still the first day in the week. This is for Jira version 7.12.3 

            Occurrence factor 50% ?? It happens every time I have to start a sprint which I have been doing quite a few times over the last 2 years that this bug has existed. I cannot use the "Duration" selector as it borks the "End date" and locks the field, preventing me from correcting it, and I have to correct the 12-hours timestamp when using the datepicker.

            This bug really isn't hard to fix and it's bugging a million people every 2 weeks.

            Deleted Account (Inactive) added a comment - Occurrence factor 50% ?? It happens every time I have to start a sprint which I have been doing quite a few times over the last 2 years that this bug has existed. I cannot use the "Duration" selector as it borks the "End date" and locks the field, preventing me from correcting it, and I have to correct the 12-hours timestamp when using the datepicker. This bug really isn't hard to fix and it's bugging a million people every 2 weeks.

              Unassigned Unassigned
              azuhra Aqqiela
              Affected customers:
              23 This affects my team