Remaining and Estimate values blank/not calculated in agile Scrum board

    XMLWordPrintable

Details

    • Bug
    • Resolution: Duplicate
    • Medium
    • None
    • Unknown
    • None

    Description

      NOTE: This bug report is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding bug report.

      Summary: Totals for "Remaining" and "Estimate" times are not displaying in the following places in an agile board (scrum):

      • Beneath the sprint, to the right of "28 of 51 issues visible".
      • "Summary of assigned work"/"Workload by assignee" pop-up dialog, in the "Original time estimate" column.

      Steps to reproduce:

      • Set up board with following config under "Estimation" tab:
        • Estimation statistic: Orignal Time Estimate
        • Time Tracking: Remaining Estimate and Time Spent
      • Add issues with time estimates to this board
      • Create a sprint with one or more of these issues

      Expected Outcome: Totals for time remaining (beneath sprint) and original estimate (workload by assignee pop-up) should be displayed.

      Actual Outcome: Totals do not display (as per screenshots).

      Additional Info:
      JIRA Cloud
      Chrome 47 + Firefox
      Worked fine several days ago—no settings/config have changed since that I am aware of.

      Please let me know if you require any further info.
      Thanks.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              88a8c485e216 Jade
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

                Created:
                Updated: