Message incorrect when ending a sprint with remaining issues

    XMLWordPrintable

Details

    • 6.07
    • Hide
      Atlassian Status as at 27 January 2016

      This has now been addressed with the related improvement GHS-7579 which is now available for both JIRA Software Cloud and JIRA Software Server.
      The server release version is 7.1.0, please see the server release notes for further details.

      Kind regards,
      Martin
      JIRA Software

      Show
      Atlassian Status as at 27 January 2016 This has now been addressed with the related improvement GHS-7579 which is now available for both JIRA Software Cloud and JIRA Software Server. The server release version is 7.1.0, please see the server release notes for further details. Kind regards, Martin JIRA Software

    Description

      When a sprint ends and issues remain, the message states the issues will be returned to the backlog
      e.g.

      3 issues were Done.
      25 incomplete issues will be returned to the top of the backlog.
      5 partially complete issues will be returned to the top of the backlog.

      In fact they will be placed in the first planned sprint if one exists as documented at https://confluence.atlassian.com/display/AGILE/Ending+a+Sprint
      Any issues not completed at the end of the sprint will be moved to the next planned sprint, as they did not meet the team's definition of "Done". If you do not have a next planned sprint, they will be returned to the backlog.

      Attachments

        Issue Links

          Activity

            People

              bmccoy bmccoy
              mjopson Martin (Inactive)
              Votes:
              16 Vote for this issue
              Watchers:
              17 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: