      Scenario:

      1. Create an issue A of type Story
      2. Add issue A to thye Sprint X
      3. Convert issue A to become an Epic
        • Issue A is still showing in the Work mode of Sprint X (to be reconsidered?)
      4. Create Sprint Y
      5. Complete Sprint X without moving issue A to the Done (last) column in Work mode
        • Issue A has now Sprint Y as a future Sprint when opening the issue
        • Issue A is not displayed on the Plan mode under Sprint Y, therefore we can no longer remove it
        • When starting the sprint Y, issue A will be effectively an Epic which has a Sprint = Sprint Y, whereas we did not account for that

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              6942b4a142c6 Pierre EK
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: