Problem Definition
Parent issue without estimate is not showing sub-task's estimate in the rapid board plan mode.
Currently, it's difficult to have the real total estimates for a sprint or somehow will cause confusion for users to plan ahead for next sprint.
Steps to reproduce
- Create a Software Project.
- Create an issue.
- Create a sub-task from the issue, set original estimate to 3w.
- Observe the parent issue, the Time Tracking is showing 3w as original estimate and remaining if the option to include sub-tasks is selected.
- Create a board for this project.
- Configure the board to estimate the issues in the Backlog using Original Time Estimate and Track time against issues using JIRA's Remaining Estimate and Time Spent fields
- Go back to the board, choose to show detail view
- Click on the parent issue
Expected result
The original estimate should show the total estimate for both the parent and sub task.
Actual result
The original estimate is showing unestimated.
Suggestion
Parent issue without estimate should include its sub-task's estimates in rapid board plan mode since the sub-tasks are not shown in the issue details.
- is duplicated by
-
JSWCLOUD-13138 Sum estimates from sub-tasks in user stories
- Closed
-
JSWCLOUD-11225 JIRA Agile should add the original time estimate of the subtasks included in a parent issue
- Closed
-
JSWCLOUD-9775 Jira Agile should show the subtask total with the Estimate field in the Details View
- Gathering Interest