Suggestion
-
Resolution: Unresolved
-
5
-
15
-
Problem Definition
By default, Advanced Roadmaps have a schedule of 8h/day. If a team has decided to for for 6h/day, Advanced Roadmaps will still convert estimation into days based on a 8h per day basis: A task that has been estimated by a team with 5d (30h) in JIRA is being turned into 3.75d.
Suggested Solution
Allow users setting working hours on plan level / Advanced roadmaps
Workaround
N/A
- relates to
-
JSWCLOUD-20434 Add the ability to schedule plans based on users capacity
- Gathering Interest