NOTE: This suggestion is for JIRA Portfolio Cloud. Using JIRA Portfolio Server? See the corresponding suggestion.
I am constantly scratching my head trying to figure out why certain items are scheduled later than i think they should be. What logic is being applied? Why is something so late? Why can't i bring it forward?
I often manage to derive the reason, after hours of trial and error, then write down a note to myself 'ah, check the rank' or 'check the dependency', or 'Portfolio honours X before Y'. I would like a report that explains step by step why Initiative 7 is scheduled for April 17th, how did Portfolio arrive at that conclusion?
Attachments
Issue Links
- is related to
-
JSWSERVER-24878 Report on how scheduling logic was applied
- Gathering Interest