NOTE: This suggestion is for JIRA Portfolio Cloud. Using JIRA Portfolio Server? See the corresponding suggestion.
Currently Portfolio supports only one type of dependency which is "B can start as soon as A is completed".
Add support for other dependencies such as Start to Finish, Finish to Finish, Start to Start, Finish to Start, or a partial overlap such as "can start when 50% is completed"
Additionally, support configuration to set the delay such as number of days before the start of another Epic/Story.
- duplicates
-
JRACLOUD-89232 Dependencies between story/epics with delay
- Closed
- is related to
-
JRACLOUD-88063 Better support for managing external dependencies
- Gathering Interest
-
JSWSERVER-24871 Support different types of scheduling dependencies
- Gathering Interest
- relates to
-
JRACLOUD-88770 support on external dependency
- Closed