Uploaded image for project: 'Jira Software Cloud'
  1. Jira Software Cloud
  2. JSWCLOUD-17392 Team-managed software projects
  3. JSWCLOUD-17590

In the new Next-gen project type, changing Epics order should "adjust" to their new position

    XMLWordPrintable

Details

    Description

      Atlassian status as of June 2020

      Hello all,

      We have recently introduced the epic panel in next gen projects! With this capability, you can order your epics by dragging and dropping epics around in the panel. The same order will be reflected in your roadmap and board.

      To learn more and/or provide feedback about the epic panel, read our community post here.

      We are closing this ticket. If you feel that this issue hasn't been fully addressed, please let us know!

      Thank you,
      Emily Chan
      Product Manager, Atlassian.

      When changing the order of the epics in a next-gen project's roadmap, it would be great if the set dates to change too, depending to each other. Example:

      Epic 1 - 1.2.2019 - 28.2.2019
      Epic 2 - 1.3.2019 - 31.3.2019
      Epic 3 - 1.4.2019 - 30.4.2019

      If I change Epic 3 to position 2 in the roadmap and would like the dates to change:

      Epic 1 - 1.2.2019 - 28.2.2019
      Epic 3 - 1.3.2019 - 31.3.2019
      Epic 2 - 1.4.2019 - 30.4.2019

      Attachments

        Issue Links

          Activity

            People

              echan@atlassian.com Emily Chan (Inactive)
              gfranck Gabriele Franck
              Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: