Bug
-
Resolution: Not a bug
-
Low
-
None
-
Severity 3 - Minor
-
Summary
Time Tracking gadget shows the sum of the Original and Remaining Time estimate.
The board shows the Remaining Sum field (where the remaining sum is sum up to parent)
It is important that there is consistency in showing the information for this fields.
Environment
Atlassian Cloud
Steps to Reproduce
- Create a Task
- Create subtasks
- Estimate the subtasks
- Check the Include Subtask in the Time Tracking gadget on the Task
Expected Results
Original Time Estimate and Remaining Time Estimate fields have the same value on the board backlog and in the Time Tracking gadget.
Actual Results
- Original Time Estimate and Remaining Time Estimate show the sum in the Time Tracking gadget.
- Original Time Estimate and Remaining Time Estimate show no value on the board Backlog. The issue is not estimated.
Workaround
-
- is incorporated by
-
JSWCLOUD-9167 Sum estimates from sub-tasks in user stories
- Closed
- was cloned as
-
JSWCLOUD-16215 Have consistency for the Original and Remaining Time estimate fields on Time Tracking gadget and the Board backlog