The Target Start and End Date validation is incorrect when filled manually

XMLWordPrintable

    • Type: Bug
    • Resolution: Unresolved
    • Priority: Low
    • None
    • Affects Version/s: 8.20.10, 8.22.1
    • Component/s: Issue - Fields
    • None
    • 8.2
    • 2
    • Severity 3 - Minor
    • 1

      Issue Summary

      The Target Start and End Date validation is incorrect when filled manually

      This is reproducible on Data Center: (yes)

      Steps to Reproduce

      1. Add the Target Start and Target End to the Create Screen
      2. Open the Create Issue Dialogue
      3. Manually enter two values of the dates (don't use the calendar picker)
      4. Target Start - 10/10/2022 and Target End - 4/11/2022 (the format is set to d/MM/YYYY)

      Expected Results

      As the Target End is after Target Start, this validation should pass

      Actual Results

      The error "Target end date must be after target start date" is thrown

      It appears that when the dates are filled manually, the validation is done only on the basis of the day field or the columns are not recognised in the right order

      Workaround

      Use the calendar picker to choose the date instead