Exclude Stories from WIP Limit

    XMLWordPrintable

    Details

    • Feedback Policy:
      We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      Description

      Actual Behavior:

      • In the Agile board configuration, Column management, I can select a column constraint from the following options:
        1. None
        2. Issue Count
        3. Issue Count, excluding sub-tasks

      Expected Behavior:

      • There should be fourth option "Only sub-tasks"

      Context

      Our main working items after Planning 2 are sub-tasks we have created with the whole team. Each sub-tasks should be a maximum of 1 day effort. I as a scrum master want to restrict the number of open sub-tasks using the WIP limit. The problem is, that also the stories will count in. To work around that, we keep the story OPEN until we have resolved all sub-tasks an then also resolve the Story. That has the disadvantage that we cannot calculate cycle time for stories.

       

        Attachments

          Activity

            People

            Assignee:
            Unassigned
            Reporter:
            jan.wedel Jan Wedel
            Votes:
            14 Vote for this issue
            Watchers:
            6 Start watching this issue

              Dates

              Created:
              Updated: