Remaining estimate is inconsistent when editing a worklog down

XMLWordPrintable

      NOTE: This bug report is for JIRA Server. Using JIRA Cloud? See the corresponding bug report.

      Summary

      Editing existing Work logs while having 'Adjust Automatically' selected causes the Estimations to be calculated differently than expected.

      Steps to Reproduce

      Scenario 1

      1. Create a Task with an Original Estimate of 6 hours
      2. Log 8 hours of work
      3. Edit the work logged to 6 hours

      Scenario 2

      1. Create a task with no Original Estimate
      2. Log 8 hours of work
      3. Edit the work log down to 2 hours of work

      Expected Results

      Scenario 1: Results in 0 hours remaining
      Scenario 2: Results in 0 hours remaining

      Actual Results

      Scenario 1: Results in 2 hours remaining
      Scenario 2: Results in 6 hours remaining

      Workaround

      Do not use Automatic calculation, manually enter what time remains.

      Original Description

      The remaining estimate field is incorrect in the following situation:

      • Task entered with original Estimate of 6 hrs
      • Worklog entered (8 hrs)
      • Worklog edited down to 6 hrs

      After doing this:

      Original Estimate = 6 hrs
      Time Spent = 6 hrs
      Remaining Estimate = 2 hrs

      In this situation, shouldn't the remaining estimate be 0 hrs?