Problem
As mentioned here, to complete a sprint, all subtasks from a Done parent must also be set to Done before it is possible to complete the sprint.
When the subtasks are complete, however, if any of the subtasks are in a status that is not mapped on the board, the error displayed simply mentions that there are incomplete subtasks that need to be complete:
Failed to complete sprint: Sprint cannot be completed as there are incomplete subtasks on the following issues: <issue-key>
This video shows both how to replicate the problem and how to solve it: CompleteSprint-SubtaskNotMapped.mp4![]()
Why is it important?
Without a detailed error, it is hard to understand why the sprint is not deleted/completed, as the subtasks may already be Done, but the status is not mapped.
Suggested resolution
Improve the error message to a more detailed message on why the sprint can't be deleted/completed.
Workaround
Map the status of the subtask on the board and ensure the subtask is in a Done status.
This video shows both the problem and how to solve it: CompleteSprint-SubtaskNotMapped.mp4![]()