Suggestion
-
Resolution: Unresolved
-
None
-
2
-
Issue Summary
The Sprint field displays the Sprint's manually set end date and not the actual completion date.
Steps to Reproduce
- Create a Sprint.
- Ensure to set the required Start date and End date.
- Complete the sprint before/after the end date set.
- Verify the Sprint field for any one issue to check the completed sprint information.
Expected Results
The Sprint field should display the actual completion date of the sprint in the issue view screen.
Actual Results
The Sprint field displays the end date manually set for under sprint details, in the issue view screen.
Workaround
Currently there is no known workaround for this behavior for completed Sprints. A workaround will be added here when available
For future sprints: Before completing the sprint, you can edit the sprint date and set it to the desired date to ensure that the correct date appears in the Sprint field.
- Reference: Edit a sprint in a company-managed project