      Problem Description

      • Our team schedules issues using the timeline view. Having weekends/non-working days in play makes it difficult to schedule items that span multiple work weeks.
      • An issue that starts on Friday and ends on Monday would appear to take 4 days instead of 2
      • This also impacts the also affects the accuracy of the reporting tools.
      • Readjusting schedules when items slip becomes a nightmare.

      Suggested Resolution

      Hide all non-working days from the calendar/timeline view

      Why this is important?

      This will make it much easier for teams to track accurate working days across their projects