Issue Summary
When using the Copy to clipboard feature on the List view, the Due date Field shows -1 day, other time Fields seem not affected
Steps to Reproduce
- Access the List view of a project
- Select any Issue with a Due date set
- Select the Copy to clipboard option
- Paste the data into a spreadsheet
Expected Results
The Due date Field is exported as it is
Actual Results
The Due date Field shows -1 day.

Export:
| Issue Type | Key | Summary | Status | Assignee | Due date | Priority | Labels | Created | Updated | Reporter | Parent | Development | Fix versions |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Epic | CSP-5 | Epic Sprint 1 | To Do | 2023-06-28 | Medium | 2023-06-15 | 2024-01-24 | Omar Vargas | |||||
| Epic | CSP-6 | Epic Sprint 2 | To Do | 2023-06-24 | Medium | 2023-06-15 | 2024-03-19 | Omar Vargas | Scrum Version 2 |
Workaround
Use the View all Issues tool to export the data:
| Issue Type | Issue key | Issue id | Summary | Priority | Status | Created | Updated | Due date | Time Spent | Custom field (Actual start) | Custom field (Start date) |
| Epic | CSP-6 | 10093 | Epic Sprint 2 | Medium | To Do | 15/Jun/23 10:25 AM | 19/Mar/24 11:34 AM | 25/Jun/23 12:00 AM | 11/Jun/23 12:00 AM | ||
| Epic | CSP-5 | 10092 | Epic Sprint 1 | Medium | To Do | 15/Jun/23 10:22 AM | 24/Jan/24 1:39 PM | 29/Jun/23 12:00 AM | 15/Jun/23 12:00 AM |