Sprint Burndown Gadget not updating automatically with Next Sprint Due enabled

XMLWordPrintable

    • 5
    • Severity 3 - Minor
    • 1

      Issue Summary

      In a dashboard with Sprint Burndown Gadget, the sprint being considered is not automatically updated to the next sprint due after a sprint is completed even with the "Next Sprint due (auto)" option enabled.

      Steps to Reproduce

      1. Configure the Sprint Burndown Gadget with a sprint and the Next Sprint due (auto) option enabled.
      2. Complete the sprint.
      3. Other gadgets will update to the next sprint due correctly, but not the Sprint Burndown Gadgets.

      Expected Results

      Sprint Burndown gadget updates to the next sprint due automatically.

      Actual Results

      The update does not occur automatically, it is necessary to manually update the sprint.

      Workaround

      Update the sprint manually.