Summary
If you add Epics to a version, the Version report considers Epics as unestimated items, but it is not possible to set estimation to Epics
Environment
- Jira Cloud
Steps to Reproduce
- In a SCRUM project creates one epic and some stories
- In the same project, create one version and one sprint
- Set estimation to the stories
- Add the stories to the version and to the sprint
- Start the sprint, complete the issues and complete the sprint
- Release the version
- Check the Version report
Expected Results
The report considers only the estimated and unestimated stories
Actual Results
The report considers only all the stories and the epic also
Notes
Workaround
No workarounds for now