Problem Definition
The release concept is more applicable to development team but less applicable when it comes to professional services team and during customer project implementations.
Suggested Solution
It would be great if if users are able to choose to work with releases or not - and than define end date on specific stories that will basically will be the milestones.
- is duplicated by
-
JRACLOUD-89599 Allow to schedule a work item with manually configured start and end date
- Closed
- is related to
-
JPOSERVER-1128 Ability to define start and end date on an issue with out relate it to a release
- Closed
-
JRACLOUD-88010 As a project manager I want to set fixed start date and / or fixed end date for specific Initiatives / Epics / Stories.
- Gathering Interest