Suggestion
-
Resolution: Timed out
-
0
-
2
-
As a user, I would like to be able to see the workload evenly distributed amongst all iterations of a task.
Currently, Advanced Roadmaps linearly decreases the estimate for each iteration based on the team capacity and shows "all green" for each iteration, even though the workload overall is too much for the assigned team. Only in the last iteration it shows the actual overload.
If the estimate was evenly spread amongst the timeline of the task, this would be immediately visible and measures could be taken more effectively, rather than checking on the last iteration of each task. This is eg. how BigPicture handles the capacity planning.