Time tracking, working hours per day is not respected by Advanced Roadmaps

XMLWordPrintable

    • Type: Bug
    • Resolution: Fixed
    • Priority: Low
    • Component/s: Plans - Timeline
    • None
    • 3
    • Severity 3 - Minor

      Issue Summary

      Time tracking, working hours per day is not respected by Advanced Roadmaps

      Steps to Reproduce

      1. Set 7h working hours per day in time tracking
      2. Set Remaining Time in Jira to 35h. In the Jira issue, it is shown as 1w or 35h, which is fine.
      3. In the plan, it should show 5d. But shows 4.375d which translates to 8h per day.


      Expected Results

      In the plan, it should be shown as 35h or 5d. It should follow the time tracking settings.

      Actual Results

      In the plan, it translates to 8h per day. It is following the default time tracking settings.

      Workaround

      No workaround

        1. Screenshot 2020-09-30 at 14.00.42.png
          65 kB
          Ratnarup
        2. Screenshot 2020-09-30 at 14.01.06.png
          16 kB
          Ratnarup
        3. Screenshot 2020-09-30 at 14.01.15.png
          8 kB
          Ratnarup
        4. Screenshot 2020-09-30 at 14.01.30.png
          55 kB
          Ratnarup

            Assignee:
            Quentin Feyaerts
            Reporter:
            Ratnarup (Inactive)
            Votes:
            2 Vote for this issue
            Watchers:
            6 Start watching this issue

              Created:
              Updated:
              Resolved: