Consider number of already completed sprints for teams connected to board issue sources

XMLWordPrintable

    • 0
    • 3

      NOTE: This bug report is for JIRA Portfolio Cloud. Using JIRA Portfolio Server? See the corresponding bug report.

      Problem Summary

      When new sprints are forecasted by Portfolio, it uses the count of sprints on the plan as basis for the sprint numbering, not the total count or the number of the latest sprint.

      Expected Behavior

      Use the same engine as Agile does when forecasting sprints, where it gets the number of the latest sprint.

      Actual Behavior

      Because of this, it doesn't matter if I had 30 sprints completed in the past, if I only have 3 active or future sprints, JPO will start counting on Sprint 4.

      Steps to Reproduce

      1. Create a Scrum Board;
      2. Create 2 sprints;
      3. Complete 1 sprint;
      4. Create a Portfolio plan and connect to the board;
      5. Forecasted sprints will start on Sprint 2;

      Workaround

      No workaround available at this time.

        1. sprints.JPG
          14 kB
          Stanisław Matczak

              Assignee:
              Unassigned
              Reporter:
              Stanisław Matczak
              Votes:
              13 Vote for this issue
              Watchers:
              14 Start watching this issue

                Created:
                Updated:
                Resolved: