Issue Summary
When moving a sub-task to Done in a kanban board, the "Update Parent Issue" pop-up is displayed even if there are sub-tasks opened for the mentioned parent issue, as long as they are not returned by the board filter.
Steps to Reproduce
- In a Kanban project, create a parent issue (Task, Story or Bug)
- Under that issue, create two sub-tasks
- Add the component "test" to one of the sub-tasks
- Edit your board filter to "Project = xyz and component = test", so only one of the sub-tasks above will be displayed
- Navigate to the Kanban board and move the sub-task to "Done", by dragging and dropping it in the rightmost board column
Expected Results
As there are still open issues under the parent, the "Update Parent Issue" pop-up should not appear.
Actual Results
the "Update Parent Issue" pop-up is displayed.
Workaround
Edit the board filter to display all the sub-tasks under the parent.
- is related to
-
JRACLOUD-93289 The "Update Parent Issue" pop-up is incorrectly displayed if there are sub-tasks opened out of the board view
-