When two different users perform bulk operations simultaneously, JIRA will show the results of the operations erroneously.
Steps to Reproduce
- User A starts a bulk update of a large number of issues: 1k for example.
- User B start a bulk update of a few issues: 5 for example.
Expected Results
Each user will see the results of their respective bulk action.
Actual Results
Both users will "Acknowledge" user's B bulk operation, as it has started later, and be redirected to User's B query on the Issue Navigator.
Additionally, it will no longer be possible to see user A bulk operation progress.
Notes
Even though the progress will not be available via UI. User's A bulk operation will keep running on the background and will eventually be successfully completed.
- is related to
-
JRACLOUD-66949 Rebuilding Index or bulk editing while Cloning or performing other tasks crashes both tasks
-
- Closed
-
-
JRACLOUD-67273 Cloning an issue during a CSV import causes CSV to run only in background and NPE
-
- Closed
-