Time Tracking - The estimate of hours of a task does not include the total of the subtasks that contains in Issue Navigator

    XMLWordPrintable

Details

    • Suggestion
    • Resolution: Won't Do
    • None
    • Jira 4.3.4
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

    Description

      NOTE: This suggestion is for JIRA Cloud. Using JIRA Server? See the corresponding suggestion.

      I want that the Remaining Estimate column in "Issue Navigator" shows the value depending of the subtasks, too; equals to when you are in dispform and you click in "Include subtasks".

      Anyway, the remaining estimate on the Issue Navigator is only able to display the Remaining Estimate from the parent issue without including the ones from the sub-tasks.

      Example:

      Parent task - Remaining Estimate: 3w
      Subtask - Remaining Estimate: 1w 1d

      Displayed on Remaining of Parent task View Screen / dispform after ticking the "Include Subtasks": 4w 1d

      Displayed on the Issue Navigator: 3w

      What should be displayed: 4w 1d

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              bf0a83ac7ea3 David Uru
              Votes:
              3 Vote for this issue
              Watchers:
              6 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: