Define story point supply per resource

This issue belongs to an archived project. You can view it, but you can't modify it. Learn more

    • Type: Suggestion
    • Resolution: Unresolved
    • None
    • Component/s: Resources
    • 0
    • 2

      NOTE: This suggestion is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding suggestion.

      Having a scrum team and calculating with story points I want to be able to define a story point supply for every resource.
      Currently JPO only supports the velocity definition for the whole team.

      Workaround:

      You can adjust weekly hours as a proxy to reflect story points per team member.
      The proportion of weekly hours per team member equates to the proportion of story points assigned to members from the pool of team points.

      E.g: Team X has 30 pts
      Case 1:
      Member A - 40 weekly hrs = 10 pts
      Member B - 40 weekly hrs = 10 pts
      Member C - 40 weekly hrs = 10 pts

      Case 2:
      Member A - 60 weekly hrs = 15 pts
      Member B - 40 weekly hrs = 10 pts
      Member C - 20 weekly hrs = 5 pts