Uploaded image for project: 'Advanced Roadmaps'
  1. Advanced Roadmaps
  2. JPOSERVER-315

Stages scheduled concurrently rather than sequentially

This issue belongs to an archived project. You can view it, but you can't modify it. Learn more

    XMLWordPrintable

Details

    • Bug
    • Resolution: Answered
    • Medium
    • None
    • None
    • None
    • None

    Description

      NOTE: This bug report is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding bug report.

      SYSTEM:

      JIRA portfolio version: 1.9.2
      JIRA version: 6.3.15

      SCENARIO:

      • Our "definition of done" is typical. Both implementation and testing must occur for a story to be complete.
      • Although there is some back-and-forth, the bulk of those two activities occur in two distinct, sequential stages.
      • We want most stories to be completed in a single sprint.
      • As suggested by "Understanding Stages and Skills" at https://confluence.atlassian.com/pages/viewpage.action?pageId=715262985, we are using stages for sequential activities.

      >"Typically, stages are used for activities that need to be done sequentially per work item."
      >...
      >"Another likely setup could be:
      >"* Design
      >"* Implementation
      >"* Test"

      • In "Configure stages and skills," I've created two stages: "Development" and "QA."
      • On the "People" page, I've created a team with two people, one checked for each stage.
      • On the "Backlog" page, I've created a single story, assigned to that team.
      • To allow both stages to be scheduled within a single sprint, I've turned off the "stage/sprint constraints" in the plan configuration accessed via "Plan>Configure," on the page accessed with "Planning>Scheduling."
      • I've configured the schedule views at the bottom so that "Grouping" is by "Members."
      • I've examined the Epics, Stories and Capacity views.

      EXPECTED:

      • The QA stage will occur, and should be scheduled, after the development stage.

      OBSERVED:

      • The QA and development stages are displayed as concurrent, at least in the Epics, Stories and Capacity views.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              7245687d08cb Andrew Thomas
              Archiver:
              atibrewal@atlassian.com Aakrity Tibrewal

              Dates

                Created:
                Updated:
                Resolved:
                Archived: