Leaving team capacity blank resulted in Portfolio schedule issues using default 200 weekly hours

This issue belongs to an archived project. You can view it, but you can't modify it. Learn more

XMLWordPrintable

    • Type: Bug
    • Resolution: Fixed
    • Priority: Low
    • 3.24.0
    • Affects Version/s: 3.9.0
    • Component/s: Scheduling
    • 2
    • Severity 3 - Minor

      Issue Summary

      Leaving team capacity blank resulted in Portfolio schedule issues using default 200 weekly hours.

      Environment

      • Portfolio improved interface

      Steps to Reproduce

      1. Create a new plan with the Kanban team type.
      2. Populate some Stories with their estimation.
      3. Under the team capacity, you will see something like below:
      4. Do the auto-schedule and you will see Portfolio scheduling using 200 hours instead of 40:

      Expected Results

      The Portfolio is scheduling using the shown 40 weekly hours.

      Actual Results

      The Portfolio is scheduling using the default 200 weekly hours.

      Notes

      • Only happens in KANBAN team type in the Improved Interface.

      Workaround

      Explicitly set the team capacity will overwrite the default 200 weekly hours.