Improve documentation around scheduling behaviour of unestimated blocking issues

This issue belongs to an archived project. You can view it, but you can't modify it. Learn more

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Tracked Elsewhere
    • Icon: Low Low
    • None
    • None
    • Documentation
    • None

      From customer feedback it would seem that it is not clear that unestimated issues that block other issues will not have an impact on the scheduling of the blocked issues. There appears to be an expectation that the target end date of an unestimated issue will impact the scheduled start date of blocked issues when this is not the case. Another issue (https://jira.atlassian.com/browse/JPOSERVER-2323) has been raised to make some changes to the scheduling algorithm, but it might be prudent to update the existing documentation in the meantime to clarify the situation.

      These the suggested pages to consider improving (although there may be others):

      Steps to Reproduce

      1. Create a project with issues A and B
      2. Make issue B blocked by issue A
      3. Create a plan for that project
      4. Give an estimate to issue B
      5. Give target start and end dates to issue A
      6. Click "calculate" to schedule the issues

      Expected Results

      It could reasonably be expected that issue B will not have a calculated start date that is before the target end date of A (because it is a known date).

      Actual Results

      B will start as the same time as A (because A is not considered in scheduling because it has no estimate).

      Workaround

      Give an estimate to issue A.