Per the Documentation:
The noted Items required for the Members field to import the assignee are:
For the Jira issue assignee to show in the team member column in Portfolio for Jira, these conditions must apply:
- There is no member set in Portfolio for Jira.
- The assignee is set on the issue in Jira.
- The assignee is part of a team in your plan.
- If you've made a manual team assignment, make sure the assignee is part of that team.
- To see the assignee that is being pulled from Jira, you have to calculate your plan.
- The issue assignee import level must be set to a hierarchy level. See Configuring initiatives and other hierarchy levels.
But the requirements for calculation to associate this user is not clearly defined:
To see the assignee that is being pulled from Jira, you have to calculate your plan.
This pulls in elements from some additional documentation Scheduling and timeline, Scheduling behavior & Scheduling unestimated items to piece this behavior togather BUT does not clearly define that this also requires an estimate or a manual Sprint association for the assignee to populate in the member column with the following variables to make this true:
If Unestimated item scheduling is set to:
- Base on default estimates & a value is set for the default values (Sprint, Epic, Initiative...)
- Assignee will be populated per the user assigned to the issue in jira as a default estimate is added to un-estimated issues to allow the calculation to occur
- Base on target dates
- Requires Either an Estimate or Manual Sprint association
- Custom
- Requires Either an Estimate or Manual Sprint association
- Off
- Requires an Estimate