Schedule Dependency equal to Rank on Multiple backlog

This issue belongs to an archived project. You can view it, but you can't modify it. Learn more

XMLWordPrintable

      NOTE: This bug report is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding bug report.

      Summary

      Scheduling algorithm considers Rank first than any other values such as dependencies. When there are multiple backlogs and teams working on the same Plan, it may get an unexpected result.

      Steps to Reproduce

      Have Backlog A and Backlog B runs in parallel on two different backlogs with assigned to two different teams.

      Backlog A has the following backlog (rank in brackets):
      BACKLOGA-1 (1)
      BACKLOGA-2 (2)
      BACKLOGA-3 (3)
      BACKLOGA-4 (4)
      BACKLOGA-5 (5)

      Backlog B has the following backlog (rank in brackets)
      BACKLOGB-1 (6)
      BACKLOGB-2 (7)
      BACKLOGB-3 (8)
      BACKLOGB-4 (9)
      BACKLOGB-5 (10)

      If BACKLOGA-1 has a dependency on BACKLOGB-2 it does not schedule it straight after BACKLOGB-2 completes (which it should, because it is first in the backlog and has the highest rank).

      Expected Results

      BACKLOGA-1 scheduled right after BACKLOGB-2

      Actual Results

      BACKLOGA-1 scheduled after BACKLOGA-5

      Notes

      This is because, in scheduling, Rank is considered first then other values such as dependency. It is an expected behaviour, JPO-1531 open to adding this in the documentation.