NOTE: This suggestion is for JIRA Portfolio Server. Using JIRA Portfolio Cloud? See the corresponding suggestion.
I have a specific amount of work that my client wishes to have completed by fixed points in time.
I have created epics in a plan and assigned them to versions that have fixed start and end dates. The workload estimate is currently in excess of the resource in the portfolio plan.
What I want to achieve is:
1. Find out how much the planned capacity is in total (rather than just per individual release) for each week / month / quarter over a specific period.
2. See a capacity view that shows how much more than the existing resource is required. e.g. Planned capacity 1000 hours, 121% capacity utilization, perhaps with the excess showing in red.
Is this possible?
- is related to
 - 
                    
JPOSERVER-84 As a project manager I want to set fixed start date and / or fixed end date for specific Initiatives / Epics / Stories.
- Gathering Interest