Issue Summary
The next export date does not update even after the first scheduled job is completed in the Data pipeline schedule screen.
Steps to Reproduce
- Schedule Data pipeline export to trigger after 1 min
- Navigate to the Data pipeline schedule main screen after 1 min and check the next export scheduled date.
Expected Results
The next export date should be updated to the next schedule.
Actual Results
The next export date does not change. Same as the first scheduled date in the past.
Workaround
No workaround. Although UI displays incorrect date, export job runs correctly as initially scheduled.