Long running task view should display a red bar when the task fails, not green bar.

XMLWordPrintable

    • Icon: Bug Bug
    • Resolution: Fixed
    • Icon: Highest Highest
    • 2.3
    • 1.4.4, 2.0, 2.0.1
    • None

      When running an import / backup restore, the user is presented with a progress bar that tracks the background 'long running task' . The progress bar MUST CORRECTLY indicate the status of the process. That is, red bar for failure, green bar for success.