    Description

      Issue Summary

      • When adding a Team managed project and a Company managed project to a Jira chart, the Epic Link column shows None as the Epic's name.

      This is reproducible on Data Center: N/A

      Steps to Reproduce

      1. Create or edit a page;
      2. Add the Jira chart macro;
      3. Select Two dimensional;
      4. Select Status as the X axis on Display options;
      5. Select Epic link as the Y axis on Display options;
      6. Add a Team managed project and a Company managed project to the macro;
      7. Click on the Insert button;
      8. Publish the page;

      Expected Results

      • The Epic Link column should show the Epic's name.

      Actual Results

      • The Epic Link column shows "None" as the Epic's name.

      Workaround

      • Currently there is no known workaround for this behavior. A workaround will be added here when available