Description
Issue Summary
- When adding a Team managed project and a Company managed project to a Jira chart, the Epic Link column shows None as the Epic's name.
This is reproducible on Data Center: N/A
Steps to Reproduce
- Create or edit a page;
- Add the Jira chart macro;
- Select Two dimensional;
- Select Status as the X axis on Display options;
- Select Epic link as the Y axis on Display options;
- Add a Team managed project and a Company managed project to the macro;
- Click on the Insert button;
- Publish the page;
Expected Results
- The Epic Link column should show the Epic's name.
Actual Results
- The Epic Link column shows "None" as the Epic's name.
Workaround
- Currently there is no known workaround for this behavior. A workaround will be added here when available