Customers have noticed that the Task Report Macro in their Profiles are not sorting and displaying Tasks correctly.
Despite completing a recent task, it does not appear at the Top of the list when sorted by Completed On Descending.
This is very problematic for customers who are trying to Track the completion of Tasks as it does not provide an accurate listing by Completion Date
Environment
- Cloud
Steps to Reproduce
- Create a Task and Assign it to Yourself
- Check/Complete the Task
- View Tasks in the Task Report
- Sort by Completed On Descending
Expected Results
Task Report is Sorted Descending and the Most Recently Completed Task is at the top
Actual Results
Task was completed on 6-Jul-2018 however it does not appear:
also the Order does not appear to be descending, we'd expect June to be above March
If we sort by Appears On (Page Title), we are able to find the Task and it's reference Page and the Task's Completion Date:
Notes
This seems to occur in profiles that have a large number of Tasks
Workaround
none