Uploaded image for project: 'Bamboo Data Center'
  1. Bamboo Data Center
  2. BAM-5192

Ability to delete build working directory after a suceessful build

    • Icon: Suggestion Suggestion
    • Resolution: Fixed
    • 2.6 M4, 2.6
    • None
    • None
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

      Add a checkbox to delete the builds working directory after the build to control the amount of disk space in use

      It would be excellent if this https://extranet.atlassian.com/display/IT/2010/01/11/Pre+and+Post+scripts+on+BEAC+agents+to+clean+up+builds was incorporated into the product at a per plan level

            [BAM-5192] Ability to delete build working directory after a suceessful build

            • Should we delete a build's tmp dir - not included for now...

            yes, but I doubt bamboo can find it.

            David Cheney (Inactive) added a comment - Should we delete a build's tmp dir - not included for now... yes, but I doubt bamboo can find it.

            MarkC added a comment -
            • Default off
            • Add to bulk action
            • Be careful of Perforce.
            • Just make it part of core Bamboo
            • Should we delete a build's tmp dir - not included for now...

            MarkC added a comment - Default off Add to bulk action Be careful of Perforce. Just make it part of core Bamboo Should we delete a build's tmp dir - not included for now...

            Assigning this to James. As discussed, the plan is to create a new plugin module hook at the very end of the agent process for BCLEAN to use.

            James plans on discussing the new hook with Chai at the earliest opportunity.

            Jim Severino (Inactive) added a comment - Assigning this to James. As discussed, the plan is to create a new plugin module hook at the very end of the agent process for BCLEAN to use. James plans on discussing the new hook with Chai at the earliest opportunity.

              Unassigned Unassigned
              dcheney David Cheney (Inactive)
              Votes:
              1 Vote for this issue
              Watchers:
              0 Start watching this issue

                Created:
                Updated:
                Resolved:

                  Estimated:
                  Original Estimate - 24h
                  24h
                  Remaining:
                  Remaining Estimate - 24h
                  24h
                  Logged:
                  Time Spent - Not Specified
                  Not Specified