Notfiication sends wrong information for assigning an 'In Progress' Issue

    XMLWordPrintable

Details

    • Bug
    • Resolution: Fixed
    • Medium
    • 3.1.1
    • None
    • Email notifications
    • None

    Description

      The Notifications for 'Stop Progress' is being sent with the wrong 'changed by' user.
      If you start progress on an issue then reassign the issue to another user, the change history correctly notes down the original assignee as the user that stopped progress. However the email sent says that the new assignee has stopped the issue.

      For example under the 'Change History' Tab you see:
      Change by Test user [10/Mar/05 10:24 AM]
      Status In Progress [ 3 ] Open [ 1 ]

      But in the email you recieve:
      Work on TST-1 stopped by Administrator

      Attachments

        Activity

          People

            brian@atlassian.com BrianH
            brian@atlassian.com BrianH
            Votes:
            0 Vote for this issue
            Watchers:
            0 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: